Tahoe-Truckee Campus Overview

Project Update April 3, 2008

We have received the Caltrans permit for the Hwy 89 work. The permit allows us to close the north bound lane of Hwy 89 all day and night from May 1 until July 1. This will allow the retaining wall, utilities and bridge to be installed during the day shift. We can also close lanes at Deerfield Dr. and Hwy 89 to allow us to complete the work on the west side of Hwy 89 during day shift. The installation of utilities crossing Hwy 89, and the median work will have to be done at night as it requires south bound lane closures, and the south bound traffic is too heavy to permit daytime lane closures. The Hwy 89 work will shift to night work after July 1,we expect the night work to take about 7 weeks.

The building had scaffolding around it and plastic wrap over the scaffolding creating a relatively warm and weather proof work environment for the winter. The plastic wrap has been removed, but the scaffolding will stay in place for another month.; On the first floor about 98% of the interior walls are framed and the door frames installed. The mechanical, electrical and plumbing (MEP)rough in is about 95% complete. We are waiting for the delivery of the air handling units in mid April to complete the MEP rough and complete the wall framing. The walls and roof are about 90% insulated, and the wires for the drop ceilings are being installed. The drywall on the first floor is about 80% complete and about 30% complete on the 2nd floor. Taping and finishing of the drywall started in late March, and texturing of the drywall started this week. The Mechatronics and Biology/Chemistry classrooms are behind the rest of the building due to the need to coordinate the floor duct, casework and utilities in those rooms.

The exterior walls have the cement siding about 97% installed and all the windows are in place. The contractor conducted a successful water test on the windows to insure they will not leak after occupancy. The contractor is installing the vertical battens and window trim.

The PUD electrical department has energized the switch gear and transformer on site, the building switch gear will be energized in mid April. The elevator is on site, it will be installed once the building is energized.

Measure H

Voters of the School Facilities Improvement District Number 1 (Tahoe-Truckee Campus Area) of the Sierra Joint Community College District authorized the issuance of $35,000,000 in bonds at the November 2, 2004 General Election with a 68.8% affirmative vote. The bond funds are to be used ‘to prepare Tahoe-Truckee area students for jobs/four-year colleges, provide for lifelong learning, and accommodate increasing enrollment by acquiring, constructing, equipping, repairing buildings, sites, classrooms, labs, libraries to complete a permanent campus.’ The District sold the first issue, Series A bonds for a total of $20,000,000 on April 21, 2005, with an interest rate of 4.83%. One additional series is expected to be issued in 2006.

Link to Tahoe Master PlanThe Board of Trustees evaluated the District’s urgent and critical facility needs in the Tahoe-Truckee area, including safety issues, enrollment growth and computer technology, in developing the scope of projects to be funded in the Tahoe-Truckee area, as outlined in the Sierra College Facilities Master Plan 2015, approved by the Board of Trustees on October 14, 2003. In developing the scope of projects the faculty, staff and students have prioritized the key health and safety needs so the most critical needs are addressed. The Board conducted independent facilities evaluations and received public input and review in developing the scope of college facility projects to be funded.

The Projects to be financed by the Improvement District are a community college campus for general education which may include up to eighteen “smart” classrooms and laboratories for instruction in a broad range of liberal and fine arts, sciences, business and vocational disciplines. The campus will include library, administrative, student service, faculty offices, student commons, physical education, maintenance, and bookstore facilities. Exterior development will include parking areas, landscaping and hiking trails, and open space responsive to community conservation goals. The Projects may include land and equipment acquisition, and joint-use facilities developed in collaboration with community partners. The Projects also include Internet and cable technology upgrades to support enhanced distance learning programs, improved telecommunication systems, and to replace outdated computer equipment.

Listed projects will be completed as needed. Each project is assumed to include its share of furniture, equipment, architectural, engineering, and similar planning costs, construction management, and a customary contingency for unforeseen design and construction costs. The allocation of bond proceeds will be affected by the District’s receipt of State bond funds and the final costs of each project. The budget for each project is an estimate and may be affected by factors beyond the District’s control. The final cost of each project will be determined as plans are finalized, construction bids are awarded, and projects are completed.

Tahoe-Truckee Center homepage.

Page last updated: July 11, 2008 :
e-mail access blackboard access employment legal disclaimer contact us ©sierra college